How to Calculate Concrete for a Slab

The math behind "how much concrete do I need" — volume, waste, bags vs. ready-mix — with worked examples.

The formula

A slab is a box: length × width × depth. Keep the units straight — measure the footprint in feet and the depth in inches, then divide by 12.

Volume (ft³) = Length (ft) × Width (ft) × Depth (in) ÷ 12

Example: a 10′ × 12′ slab at 4″ thick = 10 × 12 × (4 ÷ 12) = 40 ft³.

Add waste — yes, really

Ground is never perfectly level, forms flex, and mix sticks to the wheelbarrow. Add 10% on top of the theoretical volume. For the example above: 40 × 1.10 = 44 ft³. This is the number you buy.

Bags or ready-mix?

Bagged concrete yields are standardized:

Divide your waste-adjusted volume by the bag yield and round up. For 44 ft³ with 80-lb bags: 44 ÷ 0.60 = 74 bags. That's 74 × 80 = 5,920 lb of concrete — you will feel every bag.

Ready-mix is ordered by cubic yard (1 yd³ = 27 ft³). 44 ft³ = 1.63 yd³, so you'd order 1.75 or 2 yards depending on the plant's minimum and your confidence in the forms. Most plants have a delivery minimum around 1–3 yd³ — below that, bags are cheaper.

Rule of thumb: under ~1 yd³, bagged mix usually wins on cost and control. Over ~2 yd³, ready-mix saves your back and your schedule. In between, it's a judgment call.

Skip the arithmetic

Use the concrete calculator — enter your dimensions, depth, and waste, and it returns cubic feet, yards, bag counts, and a cost estimate.

Common mistakes

Concrete slab FAQ

How do I calculate how much concrete I need for a slab?

Measure the footprint in feet and the depth in inches, then compute Length × Width × Depth ÷ 12 for cubic feet. Example: a 10′ × 12′ slab at 4″ thick = 10 × 12 × (4 ÷ 12) = 40 ft³. Add 10% waste, so you'd order 44 ft³.

How many bags of concrete do I need?

Divide your waste-adjusted volume by the bag yield and round up: 80-lb bag ≈ 0.60 ft³, 60-lb bag ≈ 0.45 ft³, 40-lb bag ≈ 0.30 ft³. For 44 ft³ with 80-lb bags: 44 ÷ 0.60 = 74 bags.

Bags or ready-mix — which is cheaper?

Under about 1 cubic yard, bagged mix usually wins on cost and control. Over about 2 cubic yards, ready-mix saves your back and your schedule. Most plants have a 1–3 yd³ delivery minimum, so below that bags are cheaper.

How many cubic feet are in a cubic yard of concrete?

27 cubic feet. Ready-mix is ordered by cubic yard, so 44 ft³ = 1.63 yd³, and you'd order 1.75 or 2 yards depending on the plant's minimum.

Before you pour