Optional — used for the cost estimate
Total volume (with waste)36.67 ft³ · 1.36 yd³
40-lb bags123 bags · $738
60-lb bags82 bags · $492
80-lb bags62 bags · $372

80-lb bag ≈ 0.60 ft³ (0.022 yd³) · 60-lb ≈ 0.45 ft³ · 40-lb ≈ 0.30 ft³. For ready-mix, order by cubic yard and add 10% for grade variance.

How the volume formula works

Concrete is sold by volume, so the first job is turning a footprint and a thickness into cubic feet. Every slab, patio, and footing is a box: length × width × depth. Measure the footprint in feet and the depth in inches, then divide the depth by 12 to bring it into feet.

Volume (ft³) = Length (ft) × Width (ft) × Depth (in) ÷ 12

The ÷ 12 is there because there are 12 inches in a foot: a 4″ slab is 4 ÷ 12 = 0.333 ft thick. Skipping that step — multiplying the footprint by 4 instead of 0.333 — is the quickest way to oversize an order. Keep the units on the label straight and the rest of the math is multiplication.

From cubic feet to bags

Bagged concrete is sold by weight, but each bag carries a published yield — the volume of wet mix it produces:

Divide the volume you need by the bag yield, then round up to the next whole bag. You can't buy two-thirds of a bag, and coming up short mid-pour is worse than having one left on the pallet — the first batch stiffens before the next one lands and you get a cold joint where the two meet.

Cubic yards and ready-mix

Ready-mix is ordered by the cubic yard. One yard is 27 cubic feet (3 ft × 3 ft × 3 ft), so convert by dividing cubic feet by 27. Most plants also have a delivery minimum — often somewhere around 1 to 3 yd³ — so on a small pour the short-load fee can outweigh the cost of the concrete itself. That minimum is the real dividing line between buying bags and calling the plant.

Waste — why you add it, and how much

The theoretical volume describes a perfect box. In the field the subgrade isn't dead level, wood forms flex under the weight of wet concrete, and mix sticks to the wheelbarrow, the chute, and the tools. That's what the waste allowance covers, and it's why the calculator defaults to 10%. Leave it in for a formed slab on compacted grade; raise it for uneven or sloped ground, or for a first pour where you don't know yet how much the forms will move. Ordering the theoretical number and hoping is not a plan — the difference is one more trip to the truck or a cold joint.

What the code says — slab thickness and footings

Two parts of the IRC 2021 govern residential flatwork, and both are worth knowing before you order:

One honest note: the IRC does not require steel in a slab-on-ground. Reinforcement in a residential slab is spec-driven, not code-driven, unless an engineer calls for it.

Worked example — 20 ft × 15 ft slab at 4″

Say you're pouring a 20-ft × 15-ft driveway slab, 4″ thick, with a 10% waste allowance. Work it in the same order the calculator does:

Bag counts, dividing 110 ft³ and rounding up:

At 4.07 yd³ this is a ready-mix pour. 184 eighty-pound bags is about 14,720 lb of mix to carry, open, and mix one wheelbarrow at a time — the bags only make sense once you've checked them against the plant's minimum and your own back.

Common mistakes

Concrete calculator FAQ

How do I calculate how much concrete I need?

Measure the footprint in feet and the depth in inches, then multiply Length × Width × Depth ÷ 12 for cubic feet. Add your waste allowance, then divide by 27 for cubic yards or by the bag yield (0.60 ft³ for an 80-lb bag) for a bag count. A 20-ft × 15-ft slab at 4″ thick is 100 ft³ before waste.

How many 80-lb bags of concrete are in a cubic yard?

45. A cubic yard is 27 ft³ and an 80-lb bag yields about 0.60 ft³, so 27 ÷ 0.60 = 45 bags. In practice you'd order a little more to cover waste.

Why add waste to a concrete order, and how much?

Because the subgrade isn't perfectly level, forms flex, and some mix is lost to tools and spillage. A 10% allowance is the calculator default; raise it for uneven or sloped ground. Coming up short means a cold joint where one batch stiffens before the next arrives.

What thickness should a slab be, and how big does a footing need to be?

IRC 2021 R506.1 sets the minimum slab-on-ground thickness at 3.5″. Footings are governed by R403.1(1), which gives minimum width and thickness for light-frame construction; the minimum is 12″ wide × 6″ thick (R403.1.1), and exterior footings must bear at least 12″ below grade (R403.1.4) and below the local frost line (R403.1.4.1).